Question: help solving this queshtion Apples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples per minute. The
help solving this queshtion
Apples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples per minute. The capacity of the second resource is 4.4 apples per minute. The first resource has 1 worker and the second resource has 4 workers. One additional worker is hired who is as productive as the current workers. Instruction: Round your answer to three decimal places. What is the new capacity of this process? apples per minuto