Question: Help Sove & Exit A pulic library plans on holding a children's event at the end of the Summer. The activities that have to be
Help
Sove & Exit
A pulic library plans on holding a children's event at the end of the Summer. The activities that have to be completed, duration of each activity, and their sequence are listed in the table below:
tableActivitytableDurationweekstableImmediatePredecessorABACADBEDCFE
a Determine the project duration.
The longest path is ACEF
weeks.
b What is the earliest start, earliest finish time, latest start, latest finish time for activity E
tableEarliest start time,Earliest finish time,Latest start time,Latest finish time,
c What is the slack for activity C
Slack for activity