Question: Help System Announcements CALCULATOR PRINTER VERSION A BACK NEXT Brief Exercise 11-4 Simba Company's standard materials cost per unit of output is $8.40 (2.00 pounds
Help System Announcements CALCULATOR PRINTER VERSION A BACK NEXT Brief Exercise 11-4 Simba Company's standard materials cost per unit of output is $8.40 (2.00 pounds x $4.20). During July, the company purchases and uses 2,160 pounds of materials costing $11,448 in making 1,200 units of finished product. Compute the total, price, and quantity materials variances. (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to 0 decimal places, e.g. 52.) Total materials variance Materials price variance $ Materials quantity variance $ Click if you would like to Show Work for this question: Open Show Work LINK TO TEXT