Question: helppp Prepare a master schedule given this information: it is now the end of week 1; customer orders are 25 for weck 2,16 for week
helppp
Prepare a master schedule given this information: it is now the end of week 1; customer orders are 25 for weck 2,16 for week 3 , 11 for week 4,8 for week 5 , and 3 for week 6 . Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there were 64 pumps in inventory at the beginning of week 1 . A production lot size of 70 . pumps is used. (Leave no cells blank - be certain to enter "O" wherever required.)