Question: helpQuestion 5 ( a ) Consider the following product structure. Four hundred ( 4 0 0 ) units of Product A are needed. How many

helpQuestion 5
(a) Consider the following product structure. Four hundred (400) units of Product A are
needed. How many units of B,C,D,E,F, and G are needed?
(5 marks)
(b) Prepare your gross requirement schedule to identify the planned-order release using
an MRP program, if the gross requirement is 5,000 units, inventory on hand is 1,200
units, and planned receipts are 800 units.
(5 marks)
(c) The Assignment Matrix below showing machine processing costs for each job. You
are required to formulate a minimum-cost assignment and form optimal assignment.
(9 marks)
(d) A work centre has five jobs assigned to it. They are labelled, in the order of their
arrival to the customer, as jobs A,B,C,D and E. The work centre may work on only
one job at a time and must complete any job it starts before starting another job.
Job A has a processing time of 4 days and due to the customer in 12 days. Job B has
a processing time of 5 days and due to the customer in 18 days. Job C has a
processing time of 6 days and due to the customer in 10 days. Job D has a
processing time of 4 days and due to the customer in 9 days. Job E has a processing
time of 6 days and due to the customer in 16 days. Using the Shortest Processing
Time(SPT) priority rule, calculate the total flow time, mean flow time and the
average lateness of these job orders.
 helpQuestion 5 (a) Consider the following product structure. Four hundred (400)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!