Question: here are 12 operations as shown in the table, and all the numbers are shown also from the current state map part. please solve the

here are 12 operations as shown in the table, and all the numbers are shown also from the current state map part.

please solve the bottleneck problem and the excess inventory problem and give a solution and estimate improvements, ( using lean manufacturing tools and methods).

draw the future state map for it. if you zoom the picture you can see the map clearly.

Operation CT (min) CO Shifts performance Availability Quality OEE
1- Milling 5 3 57.00% 83.00% 50.00% 23.66%
2- Milling 2 14.08 3 80.00% 90.00% 70.00% 50.40%
3- Leveling 6.96 3
4- Heat Treatment 4.8 3 85.00% 95.00% 85.00% 68.64%
5- Quality Control 1 3
6- Honing 10.9 30 min 3 85.00% 81.00% 69.00% 47.50%
7- Temper Furnace 1.39 3 85.00% 85.00% 80.00% 57.80%
8- Sandblasting 2.32 3
9- Coating 1.45 3
10- 'H'Embrittlement Furnace 2.78 3 72.00% 95.00% 95.00% 54.72%
11- Quality Control 2 6.05 3
12- Delivery to Warehouse 5 3

raw material supplier: Aluminium supplier.

Monthly: 3000 ordered per month

Shift: 3

The material is shipped to the company every 3 months.

Main Industry Work Plan:

- 27 working days a month.

- All production units work 3 shifts.

- Each shift is 8 hours.

There are two 15-minute breaks in the shifts and one 30-minute meal break.

Production Processes:

-Operations are written

- Those who are ready for shipment are shipped to the customer on a monthly basis.

- Raw material supply comes in 3-month periods.

Production Planning:

- Production planning department can receive orders from the customer in annual and monthly periods. After the relevant orders are added to the sales order screen, the production planning department receives the data on the sales order screen.

-By looking at the weekly capacity-load report, it is divided into weekly production numbers and MRP is run. Material orders are made based on the current stock levels in MRP. Work orders are given to production based on the customer order quantity.

- The required raw material order is sent to the purchasing department by opening a supply order from the ERP system. Supply orders are opened by looking at the lead times of the relevant stock code.

(Lead time times are calculated by looking at procurement time, purchase time, and input inspection time.)

- Orders finalized to the raw material supplier company on a monthly basis; The order form is sent to the supplier with the order form according to technical drawing. In this way, deadlines are agreed upon.

- A 1-month security stock is kept for reasons such as design errors, planning errors, production errors (waste, scrap).

The seven wastes in Lean are;

Transportation, Inventory, Motion, Waiting, Overproduction, Overprocessing and Defects

We need to eliminate these wastes.

Milling1 produces 252 parts per day, milling 2 with four machines 458 parts per day, leveling 362 parts per day, heat treatment 262 parts per day, quality control 1 produces 1260 parts per day. Normally, the company should produce 111 parts according to their order plans, but these operations produce much more, making overstock. In the honing operation, 115 pieces were produced per day, that is, there is a bottleneck. The bottleneck refers to the slowest process in production. Therefore, the speed of production depends on the bottleneck process. Therefore, improvements should be made especially in the Honing operation.

the end of the processes

SUM: 43,86 hours and 24min, lead time: 56,73 min

part1 of the maphere are 12 operations as shown in the table, and

part 2:

here are 12 operations as shown in the table, and

part 3:

here are 12 operations as shown in the table, and

1000 MILLING(1) 1 MILLING leveling Heat Treatment I I X 1 I x 1 I 162 piece X 4 I 178 piece X 2 0 1000 piece 3 DK C.T=5 DK C.T=4,80DK C.T=14,075 dk C.T-6.96DK KULLANABLRLIK: 95% availablility: 83% KULLANABLRLIK:9690 shifts:3: shifts: 3 shifts:3 shifts: 3 3000 piece Translation for the words: Dk = minutes AD or Adet = quantity or piece Kullanbilirlik = availability or use time PERF = PERFEOMANCE KALITE= quality OEE = Overall Equipment Effectiveness CT= cycle time 720 hours PERF...X57 PERF: %80 PERF: X85 main yok of all KALITE..:%50 KALITE: %70 KALITE: %85 OEE..:23,66% OEE: 50,40% OEE: 68,64% 3 min 216 hours 35 hours 38 hours 3 minute O hour 30 5 min 14.08 min 6.96 minute 4.8 minute Heat Treatment Quality control Honing Temper Furnace Sandblasting I x 1 I AV HOIST I I I 840 X1 1 X 1 X 1 X 1 50 ADET 152 ADET 0 0 0 C.T=4,80DK 3 DK 1 DK 2 DK 1 DK 1 DK 1 DK C.T=1 dk C.T=10,90 CO=30DK C.T=1,39 DK C.T=2,32 DK availablility: 95% availablility: 81% availablility: 85% shifts:3: shifts:3: shifts:3: shifts:3: shifts:3: PERF: %85 PERF: 585 PERF: %85 KALITE: %85 KALITE: 69% KALITE: %80 OEE: 68,64% QEE: 47.51% OEE: 57,80% 3 min 11 hours 1 min 32.8 hours 2 min 0 1 min 1 min 1 min 0 0 4.8 minute 1 min 10.9 min 1.39 min 2.32 Sandblasting Coating H'Embrittlement Furnace KALITE KONTROL2 I I I AV HOIST X 1 X 1 0 X1 AMBAR X 2 IS 0 0 0 0 O ADET 1 DK 1 DK 1 DK 1 DK C.T=2,32 DK C.T=1,45 DK C.T=2,78DK C.T=6,05 DK Availablity: 95% shifts:3: shifts:3: shifts:3: shifts:3 PERF: 72 % KALITE: 95% SUM: 43,86 hours and 24min OLE: 54,72 1 min 1 min 1 min O hours 0 0 0 1 min 0 5 min LEAD TIME: 56,73 min 2.32 1.45 2,78 min 6.05 min 1000 MILLING(1) 1 MILLING leveling Heat Treatment I I X 1 I x 1 I 162 piece X 4 I 178 piece X 2 0 1000 piece 3 DK C.T=5 DK C.T=4,80DK C.T=14,075 dk C.T-6.96DK KULLANABLRLIK: 95% availablility: 83% KULLANABLRLIK:9690 shifts:3: shifts: 3 shifts:3 shifts: 3 3000 piece Translation for the words: Dk = minutes AD or Adet = quantity or piece Kullanbilirlik = availability or use time PERF = PERFEOMANCE KALITE= quality OEE = Overall Equipment Effectiveness CT= cycle time 720 hours PERF...X57 PERF: %80 PERF: X85 main yok of all KALITE..:%50 KALITE: %70 KALITE: %85 OEE..:23,66% OEE: 50,40% OEE: 68,64% 3 min 216 hours 35 hours 38 hours 3 minute O hour 30 5 min 14.08 min 6.96 minute 4.8 minute Heat Treatment Quality control Honing Temper Furnace Sandblasting I x 1 I AV HOIST I I I 840 X1 1 X 1 X 1 X 1 50 ADET 152 ADET 0 0 0 C.T=4,80DK 3 DK 1 DK 2 DK 1 DK 1 DK 1 DK C.T=1 dk C.T=10,90 CO=30DK C.T=1,39 DK C.T=2,32 DK availablility: 95% availablility: 81% availablility: 85% shifts:3: shifts:3: shifts:3: shifts:3: shifts:3: PERF: %85 PERF: 585 PERF: %85 KALITE: %85 KALITE: 69% KALITE: %80 OEE: 68,64% QEE: 47.51% OEE: 57,80% 3 min 11 hours 1 min 32.8 hours 2 min 0 1 min 1 min 1 min 0 0 4.8 minute 1 min 10.9 min 1.39 min 2.32 Sandblasting Coating H'Embrittlement Furnace KALITE KONTROL2 I I I AV HOIST X 1 X 1 0 X1 AMBAR X 2 IS 0 0 0 0 O ADET 1 DK 1 DK 1 DK 1 DK C.T=2,32 DK C.T=1,45 DK C.T=2,78DK C.T=6,05 DK Availablity: 95% shifts:3: shifts:3: shifts:3: shifts:3 PERF: 72 % KALITE: 95% SUM: 43,86 hours and 24min OLE: 54,72 1 min 1 min 1 min O hours 0 0 0 1 min 0 5 min LEAD TIME: 56,73 min 2.32 1.45 2,78 min 6.05 min

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!