Question: Here are the cash flows for a project under consideration: C 0 C 1 C 2 $7,590 +$5,520 +$19,320 a. Calculate the projects net present

Here are the cash flows for a project under consideration:

C0 C1 C2
$7,590 +$5,520 +$19,320

a. Calculate the projects net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.)

b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)