Question: Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 0 1 2 3 4 A 5,600 + 1,150 + 1,150
| Here are the expected cash flows for three projects: |
| Cash Flows (dollars) | ||||||||||||||||
| Project | Year: | 0 | 1 | 2 | 3 | 4 | ||||||||||
| A | 5,600 | + | 1,150 | + | 1,150 | + | 3,300 | 0 | ||||||||
| B | 1,600 | 0 | + | 1,600 | + | 2,300 | + | 3,300 | ||||||||
| C | 5,600 | + | 1,150 | + | 1,150 | + | 3,300 | + | 5,300 | |||||||
| a. | What is the payback period on each of the projects? |
| Project | Payback period |
| A | _____ years |
| B | _____ years |
| C | _____ years |
| b. | If you use a cutoff period of 2 years, which projects would you accept? | ||||||||||||||||
|
| c. | If you use a cutoff period of 3 years, which projects would you accept? | ||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||
| d2-2. | Which projects have positive NPVs? | |||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts