Question: Here are two projects being considered by the Chase Field House to bring summer youth sports to Wilmington Delaware. Year 0 1 2 3 4

 Here are two projects being considered by the Chase Field House

Here are two projects being considered by the Chase Field House to bring summer youth sports to Wilmington Delaware. Year 0 1 2 3 4 Project A CFs - $145,000 47000 60000 68000 49000 Project B CFS -$190,000 60000 75000 80000 80000 If the Chase Field House has a desired payback of 3 years, which project should they reject? (Your answer must be 2 decimal places)