Question: Here is a CPM network with activity times in weeks: A diagram shows a critical path through A, B, C, D, E, F and G.
Here is a CPM network with activity times in weeks:
A diagram shows a critical path through A, B, C, D, E, F and G. It shows circles labeled as A (7), B (5), C (6), D (6), E (4), F (8) and (G (3). A is connected to B and E. E leads to F and G. G and B further connects to C. C and F are connected to D.
-
Determine the critical path.
multiple choice-
A-E-G-C-D
-
A-B-C-D
-
A-E-F-D
-
-
How many weeks will the project take to complete?
-
Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?