Question: Here is a CPM network with activity times in weeks: A diagram shows a critical path through A, B, C, D, E, F and G.

Here is a CPM network with activity times in weeks:

A diagram shows a critical path through A, B, C, D, E, F and G. It shows circles labeled as A (7), B (5), C (6), D (6), E (4), F (8) and (G (3). A is connected to B and E. E leads to F and G. G and B further connects to C. C and F are connected to D.

  1. Determine the critical path.

    multiple choice
    • A-E-G-C-D

    • A-B-C-D

    • A-E-F-D

  2. How many weeks will the project take to complete?

  3. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?