Question: Here is an example of a software development project with four (4) phases. Each phase should take one month to and it is estimated that
Here is an example of a software development project with four (4) phases. Each phase should take one month to and it is estimated that each phase will cost $10,000 per phase. The phases are planned to be completed one phase after the other. Today is the end of month three (3). Please calculate EV, CV, SV, CPI, SPI, TCPI and EAC (explain what the EAC results mean to you) ... Please note that EV = (%C)*(PV). EAC is equal to BAC/CPI.
Project Phases | Month 1 | Month 3 | Month 3 | Month 4 | Status at the end of Month 3 |
Requirements Definition | S ---------- F | Complete, spent $10,000 | |||
Requirements Definition | S --------- PF | -------- F | Complete, spent $12000 | ||
Development and unit testing | S ----- PF | 50% done, spent $9000 | |||
System testing and Operation | Not yet started |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
