Question: Here is an example of a software development project with four (4) phases. Each phase should take one month to and it is estimated that

Here is an example of a software development project with four (4) phases. Each phase should take one month to and it is estimated that each phase will cost $10,000 per phase. The phases are planned to be completed one phase after the other. Today is the end of month three (3). Please calculate EV, CV, SV, CPI, SPI, TCPI and EAC (explain what the EAC results mean to you) ... Please note that EV = (%C)*(PV). EAC is equal to BAC/CPI.

Project Phases

Month 1 Month 3 Month 3 Month 4

Status at the end of Month 3

Requirements Definition

S ---------- F

Complete, spent $10,000

Requirements Definition

S --------- PF

-------- F

Complete, spent $12000

Development and unit testing

S ----- PF

50% done, spent $9000

System testing and Operation

Not yet started

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!