Question: Hi can I know only What will be the project make span if activity D is reduced by 2 days (ie from 8 to 6
Hi
can I know only
What will be the project make span if activity D is reduced by 2 days (ie from 8 to 6 days).
Activity
Dependent on
Days
A
-
2
=============
B
A
4
============
C
A
6
============
D
B,C
8
==========
E
B
3
===========
F
C
3
===========
G
D,E,F
2