Question: Hi can I know only What will be the project make span if activity D is reduced by 2 days (ie from 8 to 6

Hi

can I know only

What will be the project make span if activity D is reduced by 2 days (ie from 8 to 6 days).

Activity

Dependent on

Days

A

-

2

=============

B

A

4

============

C

A

6

============

D

B,C

8

==========

E

B

3

===========

F

C

3

===========

G

D,E,F

2