Question: Hi Can you please answer the below question. Sierra Logging Company hired Reid Construction Company to build a new bridge across the Brown Trout River.
Hi
Can you please answer the below question.
Sierra Logging Company hired Reid Construction Company to build a new bridge across the Brown Trout River. The bridge would extend a logging road into a new stand of timber. The contract called for a payment of $12 million on completion of the bridge. Work was begun in 20X0 and completed in 20X2. Total costs were as follows: 20X0 .......... $ 2 million 20X1 .......... 3 million 20X2 .......... 5 million Total .......... $10 million 1. Suppose the accountant for Reid Construction Company judged that Sierra Logging might not be able to pay the $12 million. a. How much revenue would you recognize each year under current revenue- recognition standards? b. How much revenue would you recognize each year under the proposed revenue- recognition standards? 2. Suppose Sierra Logging is a subsidiary of a major wood products company. Therefore, receipt of payment on the contract is reasonably certain. How much revenue would you recognize each year under current revenue-recognition standards?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts