Question: Hi , Iam posting this question 3rd time , Please provide correct answer with explanation ( CORRECT ANSWER I WILL LIKE ) NOTE : DONT
Hi ,
Iam posting this question 3rd time , Please provide correct answer with explanation ( CORRECT ANSWER I WILL LIKE )
NOTE : DONT USE CHATGPT !! DONT ANSWER COPY PASTE
Estimated Days Job Painting Assembly Packing Total Task
Time Days until Due A 6.5 4.0 1.0 11.5 25 B 1.0 2.5 0.5 4.0 8 C 4.0 4.0 0.5 8.5 12 D 5.5 4.5 1.5 11.5 15
Consider the following job information. Each job must proceed sequentially through the different work areas, and each area can work on only one job at a time. Sequence the jobs according to the (1) first-come, first-served rule, (2) earliest due date, and (3) critical ratio. Calculate the average lateness under each rule. Which rule performs best? Click the icon to view the job information. (1) The FCFS sequence is The average job lateness under the FCFS rule is days. (Enter your response rounded to two decimal places.) (2) The EDD sequence is The average job lateness under the EDD rule is days. (Enter your response rounded to two decimal places.) (3) The CR sequence is The average job lateness under the CR rule is days. (Enter your response rounded to two decimal places.) The rule performs best
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts