Question: Hi Please help me with the below: WBS ID TASKS ID TASK NAME DURATION PREDECESSORS 1.1.1 Collect the crew from the Airport 1 A 1
Hi
Please help me with the below:
| WBS ID | TASKS | ID | TASK NAME | DURATION | PREDECESSORS |
| 1.1.1 | Collect the crew from the Airport | 1 | A | 1 day | 0 |
| 1.1.2 | Deliver the crew in Botswana | 2 | B | 1 day | 1 |
| 1.1.3 | Set up venue and equipment (General Work) | 3 | C | 1 day | 2 |
| 1.1.4 | Deploy crew on the ground on site | 4 | D | 14 days | 3 |
| 1.2.1 | Create a menu | 5 | E | 1 day | 1,2,3,4 |
| 1.2.2 | Buy supplies | 6 | F | 1 day | 5 |
| 1.2.3 | Cook | 7 | G | 14 days | 6 |
| 1.2.4 | Clean | 8 | H | 14 days | 7 |
| 1.2.5 | Secure | 9 | I | 14 days | 8 |
| 1.2.6 | Deliver the crew to the airport | 10 | J | 1 day | 9 |
Network diagram?
Gannt Graph ?
Pert time ?
Is my predecessors correct?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts