Question: high impact score A risk manager has completed a risk identification workshop for a construction project. One of the project risks is the delay in
high impact score A risk manager has completed a risk identification workshop for a construction project. One of the project risks is the delay in the shipment of some materials from another country. The risk manager and their team have determined this risk's low probability and What kind of analysis was done to determine this? Qualitative analysis Failure mode analysis Quantitative analysis Root cause analysis (RCA)