Question: Highlight you put no excel Soru 1 -The following table shows the priority relationships and estimated durations of nine activities in a project a) Draw

Highlight you put no excel
Soru 1 -The following table shows the priority relationships and estimated durations of nine activities in a project
a) Draw the project diagram.
b) Develop the project program (EST, EFT, LST, LFT).
c) Identify critical activities?
d) Calculate the project completion time?
e) Project (i) 26. day, and (ii) 20. calculate the probability that it will be finished before the day. (please normal
use the distribution table)
soru 2-In a small store there are 10 product categories with the following costs and annual demands. Do the ABC analysis for the 10 inventory items given in the table. Taking into account that resources are limited in inventory control, determine which inventory items should be given the least attention
Highlight you put no excel
Highlight you put no excel Soru 1 -The following
Soru 4 (20 puan): Asadaki tablo, bir projedeki dokuz faaliyetin ncelik ilikileri ve tahmini srelcrini gstermektedir. a) Proje diyagramn iziniz. b) Proje programin (EST, EFT, LST, LFT) gelitirin. c) Kritik faaliyetler belirleyiniz? d) Proje tamamlanma sresini hesaplaynz? e) Projenin (i) 26. gn, ve (ii) 20. gnden nce bitmi olma olaslgn hesaplaynz. (ltfen normal datm tablosunu kullannz) Soru 5 (15 puan): Kk bir magazada aadaki maliyetlere ve yllk taleplere sahip 10 rn kategorisi bulunmaktadr. Tabloda verilen 10 stok kalemi iin ABC analizini yapnz. Stok kontrolnde kaynaklarin snrl olduunu dikkate alarak, hangi stok kalemlerine en az dikkat gsterilmesi gerektiini belirleyiniz

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!