Question: his question has more than one correct answer and all must be selected. select all the statements that are true. Product-oriented layouts tend to have

his question has more than one correct answer and all must be selected. select all the statements that are true. Product-oriented layouts tend to have high levels of work-in-process inventories. A product requires 24 separate tasks, and the sum of those task times is 14 minutes; if the cycle time is 2 minutes, then at least 12 workstations will be needed. If the schedule calls for the production of 120 units per day and 480 minutes of production time are available per day, the maximum cycle time would be 4 minutes. One drawback of a product-oriented layout is that work stoppage at any one point ties up the whole ope Cycle time is the maximum time that the product is allowed at each workstation