Question: Homework 2 Problem - Chapter 13 (Add or decrease space as needed) Problem 1 (20 points): The CPM network below represents a project with the

Homework 2 Problem - Chapter 13 (Add or decrease space as needed) Problem 1 (20 points): The CPM network below represents a project with the estimated times in days: B, A, 3 D, G, 9 H, f E, 6 F a(5). Find the critical path and the project completion time. G H c(3). What is the slack for activity E