Question: Homework 4 : Labor Cost Name: ( 4 0 points ) Part 1 : Effective cost per hour 1 shift ( 8 hours ) per

Homework 4: Labor Cost
Name:
(40 points)
Part 1: Effective cost per hour
1 shift (8 hours) per day
9 holidays
10 vacation days
Fringe: 38% of base wage
Base hourly wage: 22.50 per hour
30 minute lunch (paid) plus two 15 minute breaks (paid) per day
What is the effective cost per hour per employee? Show you work for all the steps.
Part II: Reduction in labor cost
Using the calculations from above
Assume 305,025 hours of work needed every year
Assume current productivity is 70%
Project proposed to increase productivity from 70% to 80% that requires a capital investment of $4.0 million.
Note: for the purposes of this exercise you can show partial workers ex 32.3.
How many team members are required to meet the 305,025 annual hours of work at the current 70% productivity?
What is the total dollar change in labor expense from this increase in productivity from 70% to 80%?
If the company has set a payback hurdle of 2 years (not discounted cash flow) will this investment meet that hurdle? If not, what percent labor efficiency is required to hit that hurdle rounded to the nearest whole %?
Homework 4 : Labor Cost Name: ( 4 0 points ) Part

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!