Question: Homework # 6 : Julia Ficken Question 6 ( Due: 1 1 : 5 9 pm on February 4 th ) : Assume that the

Homework #6: Julia Ficken
Question 6(Due: 11:59 pm on February 4th):
Assume that the project completion time of a project follows Normal distribution. If the estimated time along the critical path of the project is 214 days with the project variance of 100??(The mean/average project completion time =214 days and the variance of the project completion time =100).
a) What is the probability that the project will take 224 days or more to complete?
b) What is the probability that the project will take between 200 to 230 days to complete? Upload your work to HW6 folder.
 Homework #6: Julia Ficken Question 6(Due: 11:59 pm on February 4th):

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!