Question: Homework: Spring 2021 SCM 301 Homework 8 Save Score: 0 of 1 pt 1 of 2 (0 complete) HW Score: 0%, 0 of 2 pts

 Homework: Spring 2021 SCM 301 Homework 8 Save Score: 0 of

Homework: Spring 2021 SCM 301 Homework 8 Save Score: 0 of 1 pt 1 of 2 (0 complete) HW Score: 0%, 0 of 2 pts Problem 1 Question Help Consider the following data for a project to install a new server at the Northland Pines High School: Activity Immediate Predecessor(s) Activity Time (days) 3 A B A 3 6 3 D E 1 5 F G 3 B B, C DE F F G, H, 1 H 6 1 J 3 5 a. Choose the correct network diagram below. O A. OB. . Oc OD SL Click to select your answer and then click Check Answer. ? parts remaining Clear All Check