Question: Homework table [ [ Activity , Description,Predecessors,Duration ] , [ A , Site cleaning, - - - , 4 ] , [ B ,

Homework
\table[[Activity,Description,Predecessors,Duration],[A,Site cleaning,---,4],[B,Removal of trees,---,3],[C,General excavation,A,8],[D,Grading general area,B,C,7],[E,Excavation for trenches,B,C,12],[F,\table[[Placing formwork and reinforcement],[for concrete]],D,E,2],[G,Installing sewer lines,F,G,5],[H,Installing other utilities,,6]]
(1) Draw project network diagrams based on the logical relationships in the table.
(2) Calculate the time parameter, determine the time of the project and the Critical Path.