Question: Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for $22,000,000; it was completed in 2019. The following cost
Horner Construction Co. uses the percentage-of-completion
method. In 2018, Horner began work on a contract for
$22,000,000; it was completed in 2019. The following cost data
for the year-ended 2018 is as follows... Cost incurred during the
year: $7,800,000... Estimated costs to complete: $5,200,000. The
following cost data for the year-ended 2019 is as follows... Cost
incurred during the year: $5,600,000... Estimated costs to complete: n/a. The amount of gross profit to be recognized on the income statement for the year ended December 31, 2019 is
a. $3,200,000.
b. $3,440,000.
c. $3,600,000.
d. $8,600,000.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
