Question: hos 1. c. Construct the PDM on the basis on the following information about the project X a Complete first the column of the duration
hos 1. c. Construct the PDM on the basis on the following information about the project X a Complete first the column of the duration b. Execute a Forward Pass to determine the FS (First Start) and the FF(First Finish) of activities. Execute a Backward Pass to determine the LS (Latest Start) and the LF(Latest Finish) of activities. d. Determine the free float of each activity and give the lengths of all paths. e. Determine the critical path and give its length. f. Draw the PDM. Activit predec Optimistic Pessimist Most Duration FS FF LS essors duration Likely based on duration duration PERT LF Float 14 | B, C ED 1 van Nu m|ss| |2|a|a|ao G Information Technology PROJECT MANAGEMENT 7e Kathy Schwalbe