Question: how do i get the earliest time for G? Relevant information for a project consisting of activities A, B, ..., His provided in the table
how do i get the earliest time for G?
Relevant information for a project consisting of activities A, B, ..., His provided in the table below and the project network is provided. Activity Immediate Predecessors Time in weeks A N/A 3 B A 3 A 6 D B, C 7 E 7 7. 5 B 5 F G DE 7 H F G N What is the earliest start time for activity G