Question: How do you complete this exercise using the diagram above? It says to assume that indirect costs are linear at $60 per day. Act. Maximum

How do you complete this exercise using the diagram above?
It says to assume that indirect costs are linear at $60 per day.
Act. Maximum Crash Time Normal Time Normal Cost B D E F G Crash Cost (Slope) 20 60 40 0 50 100 70 1 2 1 0 3 3 1 3 5 3 10 6 7 5 now on w 50 60 70 50 100 90 50 $470 E Initial project duration 19 5 6 A F G A 3 3 3 7 5 D Total direct costs 10xStep by Step Solution