Question: HOW DO YOU DETERMINE THE OVERALL PROJECT DURATION? ADD UP ALL THE DURATIONS ASSIGNED DURING THE SCHEDULING STAGE AND MULTIPLY BY 0 . 7 5

HOW DO YOU DETERMINE THE OVERALL PROJECT DURATION?
ADD UP ALL THE DURATIONS ASSIGNED DURING THE SCHEDULING STAGE AND MULTIPLY BY 0.75 TO ACCOUNT FOR ACTIVITIES OCCURRING SIMULTANEOUSLY
ONLY USE THE LENGTH OF THE PROJECT ALLOWED IN THE CONTRACT COMPLETE A FORWARD PASS ON YOUR NETWORK LOGIC DIAGRAM ADD UP ALL THE DURATIONS CREATED DURING THE SCHEDULING STAGE NONE OF THE OTRER ANSWER CHOICES
 HOW DO YOU DETERMINE THE OVERALL PROJECT DURATION? ADD UP ALL