Question: How does conciliation differ from mediation in procurement disputes? Question 2 7 Answer a . It involves a binding decision by the conciliator b .

How does conciliation differ from mediation in procurement disputes?
Question 27 Answer
a.
It involves a binding decision by the conciliator
b.
The conciliator actively suggests solutions to the dispute
c.
It is a formal legal process
d.
It does not involve a third party
Question 28
Payment disputes in procurement contracts typically occur due to:
Question 28 Answer
a.
Timely payment by the buyer
b.
Early payment by the buyer
c.
Discrepancies between invoiced amounts and agreed terms
d.
Excess funds available
Question 29
What is the primary goal of the claims and settlements process in procurement contracts?
Question 29 Answer
a.
To renegotiate the entire contract
b.
To resolve disputes fairly and ensure contract compliance
c.
To extend the project timeline indefinitely
d.
To replace the supplier if a claim is filed
Question 30
Which activity is NOT typically part of the contract closeout process?
Question 30 Answer
a.
Final inspection and acceptance of deliverables
b.
Settlement of any remaining claims
c.
Drafting a new contract for the same project
d.
Assessment of supplier performance for future contracts
Question 31
Which of the following is a critical step in the contract closeout process?
Question 31 Answer
a.
Halting all communication with the supplier
b.
Increasing the scope of the project
c.
Reviewing all contract deliverables and ensuring acceptance
d.
Ignoring unresolved issues
Question 32
Which of the following risks is associated with cost overruns in procurement contracts?
Question 32 Answer
a.
Decreased project timeline
b.
Exceeding the allocated budget
c.
Improved project outcomes
d.
Enhanced supplier relationships
Question 33
In a services contract, which party often evaluates the performance and deliverables to ensure they meet contractual terms?
Question 33 Answer
a.
Consultant
b.
Contractor
c.
Client
d.
Supplier
Question 34
To mitigate the risk of unclear contract terms, a contract manager should:
Question 34 Answer
a.
Delegate contract writing to non-specialists
b.
Use vague language to maintain flexibility
c.
Avoid including detailed specifications
d.
Ensure all terms are clearly defined and understood by all parties
Question 35
Which of the following is a common cause of contractual disputes in procurement and supplies undertakings?
Question 35 Answer
a.
Excessive communication between parties
b.
Overestimation of supplier capacity
c.
Excessive regulatory compliance
d.
Misunderstandings due to ambiguous contract terms
Question 36
What is the significance of "capacity" in the context of a valid contract?
Question 36 Answer
a.
Ensuring both parties agree on the price
b.
Ensuring the contract is signed by witnesses
c.
Ensuring both parties have the legal ability to enter into a contract
d.
Ensuring both parties are willing to negotiate
Question 37
When handling variations, why is it important to assess the impact on project cost and time?
Question 37 Answer
a.
To avoid penalties and ensure project objectives are met
b.
To increase supplier payments
c.
To eliminate the need for further variations
d.
To decrease project quality
Question 38
Which of the following is a common reason for variations in procurement contracts?
Question 38 Answer
a.
Early completion of the project
b.
Supplier refusal to negotiate
c.
Unforeseen site conditions
d.
Fixed project scope
Question 39
What is the first phase of the procurement contract negotiation process?
Question 39 Answer
a.
Bargaining
b.
Preparation and planning
c.
Implementation
d.
Agreement
Question 40
Which procurement contract management technique involves regularly comparing actual performance against planned performance?
Question 40 Answer
a.
Contract negotiation
b.
Risk avoidance
c.
Performance monitoring and reporting
d.
Supplier relationship management
Question 41
What is the legal consequence if one party fails to fulfill their obligations under a contract?
Question 41 Answer
a.
The non-breaching party can seek legal remedies.
b.
The breaching party gets a warning.
c.
There are no legal consequences.
d.
The contract is automatically void.
Question 42
In procurement contract preparation, which factor ensures that both parties understand their responsibilities?
Question 42 Answer
a.
Detailed roles and responsibilities of each party
b.
Minimal documentation
c.
Broad and general contract terms
d.
High-level project objectives
Question 43
What is a key outcome of the discussion and bargaining phase?
Question 43 Answer
a.
Completing the project
b.
Establishing a rough draft of the contract
c.
Finalizing the payment schedule
d.
Agreeing on the contract terms and conditions
Question 44
Which statement best describes litigation in the context of procurement disputes?
Question 44 Answer
a.
It is a quick and informal process
b.
It always involves a third-party mediator
c.
It is a formal legal process where disputes are resolved in court
d.
It is the first choice for most procurement disputes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!