Question: How does conciliation differ from mediation in procurement disputes? Question 2 7 Answer a . It involves a binding decision by the conciliator b .
How does conciliation differ from mediation in procurement disputes?
Question Answer
a
It involves a binding decision by the conciliator
b
The conciliator actively suggests solutions to the dispute
c
It is a formal legal process
d
It does not involve a third party
Question
Payment disputes in procurement contracts typically occur due to:
Question Answer
a
Timely payment by the buyer
b
Early payment by the buyer
c
Discrepancies between invoiced amounts and agreed terms
d
Excess funds available
Question
What is the primary goal of the claims and settlements process in procurement contracts?
Question Answer
a
To renegotiate the entire contract
b
To resolve disputes fairly and ensure contract compliance
c
To extend the project timeline indefinitely
d
To replace the supplier if a claim is filed
Question
Which activity is NOT typically part of the contract closeout process?
Question Answer
a
Final inspection and acceptance of deliverables
b
Settlement of any remaining claims
c
Drafting a new contract for the same project
d
Assessment of supplier performance for future contracts
Question
Which of the following is a critical step in the contract closeout process?
Question Answer
a
Halting all communication with the supplier
b
Increasing the scope of the project
c
Reviewing all contract deliverables and ensuring acceptance
d
Ignoring unresolved issues
Question
Which of the following risks is associated with cost overruns in procurement contracts?
Question Answer
a
Decreased project timeline
b
Exceeding the allocated budget
c
Improved project outcomes
d
Enhanced supplier relationships
Question
In a services contract, which party often evaluates the performance and deliverables to ensure they meet contractual terms?
Question Answer
a
Consultant
b
Contractor
c
Client
d
Supplier
Question
To mitigate the risk of unclear contract terms, a contract manager should:
Question Answer
a
Delegate contract writing to nonspecialists
b
Use vague language to maintain flexibility
c
Avoid including detailed specifications
d
Ensure all terms are clearly defined and understood by all parties
Question
Which of the following is a common cause of contractual disputes in procurement and supplies undertakings?
Question Answer
a
Excessive communication between parties
b
Overestimation of supplier capacity
c
Excessive regulatory compliance
d
Misunderstandings due to ambiguous contract terms
Question
What is the significance of "capacity" in the context of a valid contract?
Question Answer
a
Ensuring both parties agree on the price
b
Ensuring the contract is signed by witnesses
c
Ensuring both parties have the legal ability to enter into a contract
d
Ensuring both parties are willing to negotiate
Question
When handling variations, why is it important to assess the impact on project cost and time?
Question Answer
a
To avoid penalties and ensure project objectives are met
b
To increase supplier payments
c
To eliminate the need for further variations
d
To decrease project quality
Question
Which of the following is a common reason for variations in procurement contracts?
Question Answer
a
Early completion of the project
b
Supplier refusal to negotiate
c
Unforeseen site conditions
d
Fixed project scope
Question
What is the first phase of the procurement contract negotiation process?
Question Answer
a
Bargaining
b
Preparation and planning
c
Implementation
d
Agreement
Question
Which procurement contract management technique involves regularly comparing actual performance against planned performance?
Question Answer
a
Contract negotiation
b
Risk avoidance
c
Performance monitoring and reporting
d
Supplier relationship management
Question
What is the legal consequence if one party fails to fulfill their obligations under a contract?
Question Answer
a
The nonbreaching party can seek legal remedies.
b
The breaching party gets a warning.
c
There are no legal consequences.
d
The contract is automatically void.
Question
In procurement contract preparation, which factor ensures that both parties understand their responsibilities?
Question Answer
a
Detailed roles and responsibilities of each party
b
Minimal documentation
c
Broad and general contract terms
d
Highlevel project objectives
Question
What is a key outcome of the discussion and bargaining phase?
Question Answer
a
Completing the project
b
Establishing a rough draft of the contract
c
Finalizing the payment schedule
d
Agreeing on the contract terms and conditions
Question
Which statement best describes litigation in the context of procurement disputes?
Question Answer
a
It is a quick and informal process
b
It always involves a thirdparty mediator
c
It is a formal legal process where disputes are resolved in court
d
It is the first choice for most procurement disputes
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
