Question: How does resource scheduling reduce flexibility in managing projects? multiple choice When resources are considered, management expects the project to be completed earlier than the
How does resource scheduling reduce flexibility in managing projects?
multiple choice
When resources are considered, management expects the project to be completed earlier than the original deadline.
When constrained resources are scheduled, the first rule of thumb is to increase slack to reduce constraints.
When resources are considered, the person who schedules the resources is no longer free for other activities.
When constrained resources are scheduled, the first rule of thumb is to reduce slack to get an efficient schedule.