Question: How is technical performance typically measured on a project? Multiple choice question. By holding status meetings with the client and requesting feedback. By computing formulas
How is technical performance typically measured on a project? Multiple choice question. By holding status meetings with the client and requesting feedback. By computing formulas such as VAC, TCPI, and EAC in the earned value system. By comparing work against criteria and tolerance limits in the scope and work package documentation