Question: How long will the following project take to complete? Task Predecessor Time (days) A None 100 B A 50 C A 200 D B, C
How long will the following project take to complete?
| Task | Predecessor | Time (days) |
| A | None | 100 |
| B | A | 50 |
| C | A | 200 |
| D | B, C | 100 |
| E | D | 89 |