Question: How many days will the project be delayed if an activity on the critical path takes longer 3 days longer than expected? A not enough
How many days will the project be delayed if an activity on the critical path takes longer 3 days longer than expected?
| A | not enough information to determine | |
| B | 1 | |
| C | 3 | |
| D | there will be no delay |