Question: How many operators are required in Operation 3 if the takt time is 60 seconds and operation 1 takes 55 seconds, operation 2 takes 75
How many operators are required in Operation 3 if the takt time is 60 seconds and operation 1 takes 55 seconds, operation 2 takes 75 seconds, operation 3 takes 120 seconds, operation 4 takes 95 seconds?
2
3
4
5