Question: How many units can the system process during an eight - hour shift? What is the cycle time of the system? 2 . At what

How many units can the system process during an eight
-
hour shift? What is the cycle time of
the system?
2
.
At what rate should raw material be released to Operation A
?
Why?
3
.
If you are told that the manufacturing lead time
(
MLT
)
from raw materials to finished goods
is
2
.
5
hours, how much work
-
in
-
process
(
WIP
)
inventory is in the system
(
excluding raw
materials and finished goods
)
?
4
.
What minimal actions could you take to double capacity?
(
Assume that it is possible to obtain
funds for extra equipment or to hire extra labour, but only if you can justify the action as
necessary to increase capacity.
)
5
.
Which operation is the bottleneck of the overall system? How do you know? RAW MATERIAL -> OPTION A: 240 UNITS/HR,15 SEC/UNIT -> OPTION B: 180 UNITS/HR,20 SEC/UNIT -> OPTION C: 200 UNITS/HR,18 SEC/UNIT -> WORK IN PROGRESS -> OPTION D: 300 UNITS/HR,12 SEC/UNIT -> FINISHED GOODS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!