Question: How many workers do I need for a project that takes 20 days, with the first 3 reserved days for training? There are 20 walls

  • How many workers do I need for a project that takes 20 days, with the first 3 reserved days for training? There are 20 walls to build, and 50 walls to paint. The painting will only be done once the walls are built. It takes one worker 2 walls to build per day and 3 walls to paint per day. 10% of the walls will need to be repainted. One worker is going to quit after training, another worker is going to quit after 10 days.

Step by Step Solution

3.43 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Let the number of workers required here be X We are given here that 10 of the walls will need to be ... View full answer