Question: How should you go about assigning a date to each task? a. Work backward from your project's deadline. b. Projects to be completed in two

How should you go about assigning a date to each task?

a. Work backward from your project's deadline.

b. Projects to be completed in two weeks or less don't usually need dates.

c. Only assign dates on which you have no other commitments.

d. Work forward from the time you were notified of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To properly assign a date to each task within a project the most effective approach is to Work backw... View full answer