Question: How to find the answer for v, w, x, y, z? The demand for subassembly S is 150 units in week 7 . Each unit
How to find the answer for v, w, x, y, z?

The demand for subassembly S is 150 units in week 7 . Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 1 unit of V,1 unit of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers). The demand for subassembly S is 150 units in week 7 . Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 1 unit of V,1 unit of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts