Question: how to solve cycle time/efficiency/flow time? The following provides a process used to assemble a chair with an upholstered seat. Stations A B make the

how to solve cycle time/efficiency/flow time? The

how to solve cycle time/efficiency/flow time?

The following provides a process used to assemble a chair with an upholstered seat. Stations A B make the seat; Stations CD assemble the chair frame; Station X is where the two subassemblies are brought together. One worker is assigned to each of the stations. The line is paced using a countdown clock to synchronize production at each station. A Required time (seconds) at each station A 28 B 30 C 28 D 24 x 17 B D Cycle Time? Efficiency? Flow Time?