Question: how to solve this using forward and backward pass ? Task Name Duration (Days) A Predecessor(s) 3 B 7 C 4 D A(S-S) E A,B

how to solve this using forward and backward pass ?

how to solve this using forward and backward pass ? Task Name

Task Name Duration (Days) A Predecessor(s) 3 B 7 C 4 D A(S-S) E A,B 6 F D 5 G C,D 2 END E,F G 1. Develop a network diagram based on above data 2. What is the Total Project duration