Question: How would you interpret a hyphenated line that is above the remaining ideal work line and right downward sloping in an iterations burndown chart? Group
How would you interpret a hyphenated line that is above the remaining ideal work line and right downward sloping in an iterations burndown chart?
Group of answer choices
Ahead of schedule.
Indeterminate.
Behind schedule.
That it is the same as actual remaining work.