Question: HPHA 5311 Chapter 8: Financial Planning & Budgeting Homework Problem 3.5 Calculate each of the following based upon the data below: Total Revenue Static Budget
HPHA 5311
Chapter 8: Financial Planning & Budgeting
Homework Problem 3.5
Calculate each of the following based upon the data below:
Total Revenue
Static Budget = $1,980,000
Flexible Budget = $2,060,000
Actual Results = $2,050,000
Total Costs
Static Budget = $1,350,000
Flexible Budget = $1,675,000
Actual Results = $1,790,000
Projected Profit
Static Budget = $630,000
Flexible Budget = $1,675,000
Actual Results = $1,790,000
a. profit variance
b. revenue variance
c. cost variance
revenue variances
d. volume variance
e. price variance
cost variance
f. volume variance
g. management variance
h. Discuss the factors involved with the profit variance
i. Explain the factors contributing to the volume variance
j. Explain the factors contributing to the cost variance
Step by Step Solution
There are 3 Steps involved in it
a Profit Variance Profit Variance Actual Results Flexible Budget Profit Variance 1790000 1675000 Profit Variance 115000 b Revenue Variance Revenue Var... View full answer