Question: HPHA 5311 Chapter 8: Financial Planning & Budgeting Homework Problem 3.5 Calculate each of the following based upon the data below: Total Revenue Static Budget

HPHA 5311

Chapter 8: Financial Planning & Budgeting

Homework Problem 3.5

Calculate each of the following based upon the data below:

Total Revenue

Static Budget = $1,980,000

Flexible Budget = $2,060,000

Actual Results = $2,050,000

Total Costs

Static Budget = $1,350,000

Flexible Budget = $1,675,000

Actual Results = $1,790,000

Projected Profit

Static Budget = $630,000

Flexible Budget = $1,675,000

Actual Results = $1,790,000

a. profit variance

b. revenue variance

c. cost variance

revenue variances

d. volume variance

e. price variance

cost variance

f. volume variance

g. management variance

h. Discuss the factors involved with the profit variance

i. Explain the factors contributing to the volume variance

j. Explain the factors contributing to the cost variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Profit Variance Profit Variance Actual Results Flexible Budget Profit Variance 1790000 1675000 Profit Variance 115000 b Revenue Variance Revenue Var... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!