Question: A wastewater treatment plant has four primary clarifiers, each with diameter of 15 m and side water depth of 4 m. The aver- age

A wastewater treatment plant has four primary clarifiers, each with diameter of 

A wastewater treatment plant has four primary clarifiers, each with diameter of 15 m and side water depth of 4 m. The aver- age daily flow is 24,000 m/d. The effluent weir is located on the periphery of each tank. Calculate the surface overflow rate, detention time, and weir loading rates. If one tank is taken out of service for maintenance, what happens to the overflow rate and detention time? Is the design adequate for the average flow with the three tanks in service?

Step by Step Solution

3.48 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

L4 Paimary cclarifiers 15m Side water depth d 4m Avg duily frow 240... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!