Question: Hunter is a project manager. She is currently working on the Control Schedule process. As part of this process, Hunter has done schedule variance analysis

Hunter is a project manager. She is currently working on the Control Schedule process. As part of this process, Hunter has done schedule variance analysis as well as a review of progress reports, and reviewed the results of performance measures. As a result of this process, which of the following may occur? 


a. Change requests 


b. Scheduling software 


c. Updates to the project charter 


d. Updates to the risk register

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The Control Schedule process in project management is about monitoring the status of project activit... View full answer