Question: HW ( i ) Problem 6 - 1 9 ( Algo ) The following tasks are to be performed on an assembly line: table
HW i
Problem Algo
The following tasks are to be performed on an assembly line:
tableTASKS THAT MUSTTASKSECONDS,PRECEDEABACBDBECFDGE FHG
The workday is hours long. The demand for completed product is per day.
a Find the cycle time required to meet the desired output rate.
Note: Round your answer to decimal place.
Cycle time
seconds per unit
b What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
Number of workstations
Note: Round your answer to decimal place.
Efficiency
f Suppose that demand rose from to units per day. Determine the cycle time. Use the solution obtained in part d Note: Round your answer for cycle time down to the nearest whole number.
cycle time to
seconds, which may require rebalancing the line.
g Suppose that demand rose from to units per day. Determine the cycle time. Use the solution obtained in part d Note: Round your answer for cycle time down to the nearest whole number.
cycle time to
seconds, which may require rebalancing the line.
a Find the cycle time required to meet the desired output rate.
Note: Round your answer to decimal place.
Cycle time
seconds per unit
b What is the theoretical number of workstations required to meet the desired output rate? Note: Round up your answer to the next whole number.
Number of workstations
d Balance the line using sequential restrictions and the longestoperatingtime rule. Determine the task under each workstation and the idle time for each such task.
Note: Leave no cells blank be certain to enter O wherever required. Round your answers to decimal place.
tableWork Station,Task,Idle Time
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock