Question: HW2. Below is Project Information Table in days find: 1) The precedence diagram 2) The critical path 3) What is the probability that the project

HW2. Below is Project Information Table in days find: 1) The precedence diagram 2) The critical path 3) What is the probability that the project will finish in less 50 days 4) What is the probability that the project will finish between 40 and 60 days Task Optimistic Normal Duration Pessimistic Duration Duration Immediate Predecessors None None 2 3 4 2 3 4 B 6 7 8 5 6 7 A-Dig trench B-Level ground C - Install tank and pump D-Water pipeline E - Electricity cabling F - Test tank G-Test pipeline H-Seal pipeline 1- Pump test A 5 6 4 4 8 12 CD CD 4 5 6 G 4 EG 6