Question: I. ( 2 0 pts . ) Bonus Prohlem. You wish to build a house and you have divided the process into a number of

I. (20 pts.) Bonus Prohlem.
You wish to build a house and you have divided the process into a number of tasks, namely:
B. excawation and building the foundation,
F. raising the wooden frame,
F. electrical wiring,
P. indoor plumbing,
D. dry walls and flooring, and
I. landscuping.
You estimate the following daration for each of the tasks (in werks):
Some of the taiks can only be started when some other tawks are conmpleted. For instanen,
you can only build the frume oner the foumdation has bexe completed, i.e. F' can surt only
after 13 is completed. All the precolence conestraints are mammarized as follownc:
F' ean otart only after BI is completed,
L. can ntart only after B is completed,
E ean ntart only after F is completed,
P can start only after F is completed,
Dean start only after R is completerl,
D can start only after P is completind.
The goal is to schexdule the starting time of each tack such that the entire projost is onmpleted
as mon as powible.
As an example, here is a fesaitle schedfle with a completion time of ten weeks.
(a) Let x1 represent the week on which task i is scheduled to start for any i in{B,F,E,P,D,L}.
Ilow can the constraint "F cau start only after B is completed" be matheraatically en-
forcerd?
b) Notice that the non-linear function y = max{z1, z2,..., zn} can be modeled with n linear
constraints: y >= z1, y >= z2,..., y >= zn. Use this information to formulate the problem
as an IP.(Note: You do not need to solve this problem, only formulation is required)
 I. (20 pts.) Bonus Prohlem. You wish to build a house

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!