Question: i AM ASKING THIS QUESTION THE 2ND TIME. The last chegg expert did not do it correctly. Please show your work. This time I have
i AM ASKING THIS QUESTION THE 2ND TIME. The last chegg expert did not do it correctly. Please show your work. This time I have even given the formulas below:
Cycle time = Production time per day/ Required output per day
Theoretical minimum # of workstations required = Sum of task times/ Cycle time
efficiency of line balance = total task time/ (# of workstations x cycle time)
total idle time = workstation cycle time x (revised units- actual units)

| Task | Task Time (Seconds) | Immediate Predecessor |
| A | 15 | - |
| B | 24 | A |
| C | 6 | A |
| D | 12 | B |
| E | 18 | B |
| F | 7 | C |
| G | 11 | C |
| H | 9 | D |
| I | 14 | E |
| J | 7 | F, G |
| K | 15 | H, I |
| L | 10 | J, K |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
