Question: I cant figure out the total variable overhead cost variance. Please help Check my work mode : This shows whet is correct or incorrect for
Check my work mode : This shows whet is correct or incorrect for the work you have complested so 4 0 Required informetion Use the following information for the Quick Study below. The following information applies to the questions displayed below Mosaic Company applies overhead using machine hours and reports the following information. 10 points Actual nachine hours used (an) 5,009 hours 4.15 Actual varlable overhead rate per hour (avR) Standard varLable overhead rate per hour (s s 4.00 QS 8-19A Overhead spending and efficiency variances LO P4 Compute the variable oveshead spending varlance and the variable overhead efficiency varlance 0 Answer is complete but not entirely correct. VR 15 4700400 000400 4700 19 505 20,000 705 lanable overhead spending vvwo 1200 Favorable 020295 0 Favoatie
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts