Question: I don't understand the following question. I know the answer it E, but I'm not sure why. How is it possible to compute the NPV

I don't understand the following question. I know the answer it E, but I'm not sure why. How is it possible to compute the NPV ( = C(0) + [C(1)/(1+r)^1]...without knowing R? If it's considering Project A, the question has no indication of a cost of capital/risk associated with it. Help??

4. Bottleneck Industries is considering project A. The project has expected cash flows of -$30,000 today, $40,000 in 1 year, -$50,000 in 2 years, and $60,000 in 3 years. The weighted-average cost of capital for Bottleneck Industries is 26.53 percent. Which one of the following assertions is true?

A. The NPV of project A cannot be computed, because the projects expected cash flows are not conventional and it is impossible to compute the NPV of a project with expected cash flows that are not conventional

B. The NPV of project A equals an amount that is less than or equal to $5.00

C. The NPV of project A equals an amount that is greater than $5.00 but less than $5.00

D. The NPV of project A equals an amount that is equal to or greater than $5.00

E. Even though project As expected cash flows are not conventional and even though it is possible to compute the NPV of a project with expected cash flows that are not conventional, the NPV of project A can not be compute

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!